Bengkulu Study: Afternoon Plastering Boosts Energy Project Efficiency

In the bustling world of construction, time is money, and efficiency is the name of the game. A groundbreaking study published in Jurnal Pensil, translated to English as ‘Pencil Journal,’ has shed new light on how to maximize labor productivity, particularly in the often-overlooked task of plastering. Led by Dwi Dzulma Susanti from the State University of Bengkulu, the research delves into the intricacies of work execution times and their impact on labor productivity, with potentially transformative implications for the energy sector.

Susanti’s study, which involved direct observation over three days, revealed striking differences in productivity between morning and afternoon shifts. The findings showed that the highest productivity value was a remarkable 14.30 square meters per hour in the afternoon, while the morning shift lagged behind with a mere 6.86 square meters per hour. This discrepancy is not just a matter of numbers; it represents a significant opportunity for cost savings and project acceleration.

The Labor Utilization Rate (LUR), a critical metric in assessing efficiency, also varied significantly. In the morning, the LUR was 57.9%, but it surged to 65.9% in the afternoon. “The afternoon time was more effective than the morning time,” Susanti noted, highlighting the potential benefits of optimizing work schedules. “However, there was a significant difference in productivity between morning and afternoon time overall, and it can still be categorized as effective with a Labor Utilization Rate (LUR) value of 61.9%, which exceeds 50%.”

For the energy sector, where construction projects often involve tight deadlines and substantial budgets, these findings could be a game-changer. By understanding and leveraging the most productive times of the day, energy companies can enhance their operational efficiency, reduce costs, and accelerate project completion. This could lead to faster deployment of renewable energy infrastructure, more efficient construction of power plants, and ultimately, a more sustainable energy landscape.

The implications of this research extend beyond immediate cost savings. As Susanti’s work demonstrates, the work sampling method can provide valuable insights into labor productivity, enabling construction firms to make data-driven decisions. This approach could revolutionize project management, leading to more accurate scheduling, better resource allocation, and ultimately, more successful projects.

As the construction industry continues to evolve, driven by technological advancements and a growing emphasis on sustainability, studies like Susanti’s will play a crucial role in shaping future developments. By focusing on the often-overlooked aspects of labor productivity, researchers and industry professionals can uncover new opportunities for improvement, paving the way for a more efficient and sustainable construction sector. The insights from this research, published in Jurnal Pensil, offer a compelling case for rethinking traditional work schedules and embracing a more data-driven approach to construction management. As the energy sector continues to grow, the lessons learned from this study could prove invaluable in driving progress and innovation.